Construction site CSL Behring

​Marti Gründungstechnik AG uses four IHC-FUNDEX F2800 displacement pile drilling rigs on the impressive large construction site in Lengnau, at the foot of the Jura mountains. Those devices produce 2'500 SMARTEX full displacement piles in up to 25 meters depth. The pile foundation works will be finished by ​mid-March 2016. The new production halls are to be put into operation in 2019.​
 